Construction Draws in 2026: Lender Draw Fees, FHA's $350 Cap and Lien Waiver Statutes in 7 States
Some links pay us a referral fee; each one says so. Disclosure
Update alert · free
An email when the construction lender draw terms numbers change
When a rate, rule or filing behind this page changes: what changed, the one number that matters, and the source to check it yourself.
Quick Answer
As of November 12, 2026, the one lender in our sample that prints a dollar draw fee, Ledger, charges $350 per draw plus the inspection (its typical status inspection costs $150 to $350), runs 4 to 6 draws a build, up to 2 a month, and averages 3 to 5 business days from a clean request to the wire. Two others say the opposite: Pimlico Capital says its projects include about four free draws and no inspection fee, and Cetan Funds says it does not typically charge draw or inspection fees on residential rehab or construction projects. The federal benchmark is FHA 203(k): a consultant's draw inspection fee may not exceed $350, 10 percent of each Standard 203(k) draw is held back, funds must be released within five business days, and the maximum is five draws (Standard) or four (Limited, raised by Mortgagee Letter 2026-06 of June 23, 2026). Public lenders show the scale of the money behind draws: at December 31, 2025, Redwood Trust had commitments to fund up to $258 million of additional advances on existing residential investor bridge loans, and funded $126 million of construction draws in 2025. On our $400,000 example at Ledger's published fee and its sample 11% rate, five draws cost $22,733 of interest plus $2,500 to $3,500 of draw and inspection fees, against $36,667 of interest if the whole budget were funded on day one (our arithmetic). Seven states set statutory lien waiver forms (California, Texas, Arizona, Nevada, Georgia, Florida and Wyoming); Missouri's statute, often listed with them, contains no form.
Key Takeaways
- Draw fees are mostly unpublished. Of eight lenders whose pages we read on November 12, 2026, only Ledger prints a dollar draw fee ($350 plus inspection). Pimlico Capital and Cetan Funds say they charge none or few, and RCN Capital says only that each draw “may include processing or inspection fees.”
- Speed claims run from 24 hours (Pimlico Capital) to 3 to 5 business days (Ledger) and 5 to 7 business days for hard-cost draws (Sound Capital). Lima One says its FastTrack photo process can take as little as one business day.
- FHA 203(k) is the published federal benchmark: a $350 maximum consultant fee per draw (Handbook 4000.1, II.A.9.c.iii), a 10 percent holdback on each Standard 203(k) draw and release within five business days (Mortgagee Letter 2026-06, June 23, 2026), and at most five draws (Standard) or four (Limited).
- Redwood Trust's 2025 Form 10-K: $258 million of commitments to fund more advances on existing bridge loans, $126 million of construction draws funded in 2025 and $2,253 thousand of bridge loan holdbacks on the balance sheet. Velocity Financial's HUD-backed construction loan shows $22.0 million unfunded at December 31, 2025 and $8.6 million at September 30, 2026.
- Of the seven states whose statutes we saved, four (California, Texas, Arizona, Nevada) prescribe four forms (conditional and unconditional, progress and final), Georgia prescribes two, Florida offers two but does not make them mandatory, and Wyoming prescribes a single form with no conditional or unconditional split.
- On a $400,000 budget released in five draws, Ledger's published $350 draw fee and typical $150 to $350 inspection add $2,500 to $3,500, and interest on the drawn balance at its sample 11% rate is $22,733 over a 10-month build (our arithmetic). Drawing in stages saves $13,933 of interest compared with day-one funding.
CSV · 73 rows
Construction draws: lender-published draw terms, SEC filings, FHA 203(k) draw rules and state lien waiver statutes, November 2026
73 rows: draw terms published by eight lenders, Redwood Trust and Velocity Financial filings, HUD Mortgagee Letter 2026-06 and Handbook 4000.1 draw rules, seven state lien waiver statutes and our five-draw example. One source per row.
What a draw is and why the lender controls it
A construction or heavy-rehab loan does not put the whole budget in your account. The lender funds the first piece at closing (the lot or the purchase) and keeps the rest as a holdback. Redwood Trust's 10-K defines the term for its bridge loans: holdbacks “represent amounts withheld from the initial loan proceeds and are subsequently disbursed to the borrower to be used in the construction, rehabilitation or purchase of the mortgaged property or to fund interest on the bridge loan.” Each release is a draw. You pay interest only on what has been drawn, which is why the draw schedule changes your carrying cost, and an inspector or a photo review gates each release. For the loan terms themselves (leverage, rates, term) see our page on ground-up construction loans; for the owner-occupant version see construction-to-permanent loans. This page covers what those pages leave out: what each draw costs, how long it takes and what paperwork the contractors must sign.
What lenders publish about draws
Draw terms sit in lenders' FAQ and blog pages rather than in rate sheets, and they are claims, not records of funded loans. We read eight on November 12, 2026 and saved each page that day.
Draw terms as published by eight lenders, read November 12, 2026
| Lender | Draw fee | Inspection | Turnaround | Holdback or retainage |
|---|---|---|---|---|
| Ledger | $350 plus inspection per draw; 4 to 6 draws typical, up to 2 a month | $150 to $350 status inspection; $350 to $750 fund control (netted from the draw) | 3 to 5 business days, request to wire | Usually 5-10% of each draw, released with the final draw |
| Pimlico Capital | About 4 free draws per project, then a flat fee (amount not published) | No inspection fee stated; virtual inspections for most draws | 24 hours average | Says it does not hold back 10% at every draw |
| Cetan Funds | Not typically charged on residential rehab or construction | Not typically charged | 24 to 48 hours, reviewed in-house | Not stated |
| Lima One Capital | Not stated | Inspector, or FastTrack photo upload by smartphone app | As little as 1 business day with FastTrack | Not stated |
| Sound Capital | Not stated | Ordered by the lender | 1 to 3 business days (soft-cost draws); 5 to 7 (hard-cost), or 4 to 5 in a second answer | Retainage may be withheld until completion |
| Backflip | Not stated | Appointments usually within 48 hours; video for visible items | Goal of 2 to 3 business days from the inspection report | Not stated |
| AHL | Not stated | Digital draw inspections | 48-hour turnaround on inspections | Not stated |
| RCN Capital | Each draw may include processing or inspection fees; no amount | Third-party or lender inspection | Some lenders 3 to 5 business days (general guidance) | Not stated |
Three readings follow. First, the only published per-draw dollar figure we found from a lender is Ledger's $350 draw fee; the typical $150 to $350 inspection is Ledger's own range, not a fee schedule. Second, the free-draw offers are limited: Pimlico Capital says about four and then a flat fee it does not print, so the count of draws in your plan matters as much as the price. Third, speed is claimed in hours by lenders that review in-house and in business days by lenders that send an inspector; a draw cannot be faster than your contractor's paperwork. Ask each lender for its fee schedule in writing, because a number that is not on the page is a number you will meet at the closing table.
What public lenders' SEC filings say about holdbacks and draws
Two public companies that lend to investors describe the mechanics in their filings, which is a harder source than a marketing page.
- Redwood Trust (CIK 930236), Form 10-K for 2025, accession 0000930236-26-000007. It reports “commitments to fund up to $258 million of additional advances on existing residential investor bridge loans,” $92 million of it on loans in securitizations co-sponsored by one of its joint ventures. Its 2025 fundings of investor bridge loans include, in the filing's words, “$126 million of construction draws,” $88 million of them on loans sold to joint ventures, and its balance sheet carries $2,253 thousand of bridge loan holdbacks ($2,148 thousand a year earlier). The 10-K also says its platform “may utilize third-party inspectors in connection with funding advances,” who “may be required to certify a borrower's eligibility for advances based on the achievement of construction milestones.” The filing adds that the commitments are generally subject to loan covenants and “other terms regarding advances that must be met before we fund the commitment”: a draw is a conditional promise, not a deposit.
- Velocity Financial (CIK 1692376), Form 10-K for 2025, accession 0001193125-26-102677, and Form 10-Q for the quarter ended September 30, 2026, accession 0001193125-26-450404. The 10-K says that in June 2018 it added “a second short-term, interest-only loan product which allows borrower draws for rehabbing residential rental property.” Its majority-owned Century unit originated a $25.9 million government-backed construction loan in September 2025 whose unfunded portion was $22.0 million at December 31, 2025 and $8.6 million at September 30, 2026, so about $17.3 million had been funded or sold by then (our arithmetic). The filings do not give Velocity's per-draw fees or inspection rules for investor loans.
The filings of Rithm Capital (Genesis Capital), Ready Capital and Broadmark were not read for this page and are not scored.
The federal benchmark: FHA 203(k)
FHA's rehabilitation loan is the only program whose draw rules are published as rules. It is for owner-occupants, so it is a benchmark rather than a tool for an investor, but its numbers show what a conservative draw process looks like. Mortgagee Letter 2026-06 (June 23, 2026) and HUD Handbook 4000.1 say:
FHA 203(k) draw rules, read November 12, 2026
| Rule | What the document says | Where |
|---|---|---|
| Maximum draws, Standard 203(k) | “a maximum of five draw requests (four intermediate and one final)”; a draw can have several disbursements | Mortgagee Letter 2026-06 |
| Maximum draws, Limited 203(k) | “a maximum of four draw requests per contractor”: initial at closing, up to two intermediate, one final | Mortgagee Letter 2026-06, effective June 23, 2026 |
| Holdback | “must hold back 10 percent of each draw request,” unless a subcontractor is 100 percent complete and lien waivers are provided | Mortgagee Letter 2026-06, II.A.8.a.xviii(C)(1) |
| Release time | “within five business days after receipt of a properly executed draw request and title update when necessary” | Mortgagee Letter 2026-06 |
| Consultant draw inspection fee | Reasonable and customary for the area, “provided the fee does not exceed a maximum of $350” per draw request | Handbook 4000.1, II.A.9.c.iii |
| Lien waivers | Obtained “at the time of any Disbursement of funds,” with a partial conditional waiver for completed work items | Handbook 4000.1, II.A.8 |
| Final holdback | May be kept up to 35 days, or the state lien-filing period if longer, to comply with state lien waiver laws | Handbook 4000.1, II.A.8 |
On an $80,000 draw, the 10 percent holdback is $8,000 held until the end (our arithmetic). The letter says its changes will be written into a forthcoming update of the Handbook, so the Handbook text we read may lag the letter; check both before relying on a figure.
Lien waiver statutes in seven states
A lien waiver is the contractor's or supplier's signed statement that it has been paid and gives up its mechanic's lien for that amount. Lenders ask for them with every draw: Ledger's draw checklist lists “Conditional lien waivers for this draw” from the contractor and every sub and supplier paid out of it, and “Unconditional lien waivers for the prior draw.” A conditional waiver takes effect when payment clears; an unconditional one takes effect when signed, so signing one before the money arrives gives the right up for nothing. Some states fix the wording by statute. We read the statute text in the states below on November 12, 2026.
State statutes that prescribe lien waiver forms (seven states read)
| State | Statute | Forms prescribed | What the statute says about other forms |
|---|---|---|---|
| California | Civil Code 8132, 8134, 8136, 8138 | Four: conditional and unconditional, progress and final | Section 8132: a waiver “shall be null, void, and unenforceable unless it is in substantially the following form” Effective January 1, 2011, operative July 1, 2012 |
| Texas | Property Code 53.281 to 53.284 | Four: conditional and unconditional, progress and final | Unenforceable unless it substantially complies with a 53.284 form; no one may require an unconditional waiver unless paid in good and sufficient funds (53.283, effective January 1, 2012) |
| Arizona | A.R.S. 33-1008 | Four: conditional and unconditional, progress and final | Unenforceable “unless it follows substantially the following forms” |
| Nevada | NRS 108.2457 | Four: conditional and unconditional, progress and final | Unenforceable unless it is “in the following forms in the following circumstances” |
| Georgia | O.C.G.A. 44-14-366 | Two: interim payment and final payment, in at least 12-point font | A statement counts only if made on the prescribed form and the claimant has received payment |
| Florida | Statutes 713.20(4) to (8) | Two: progress payment and final payment, “may be” in substantially this form | A person “may not require” a different form (subsection 6), but a non-conforming waiver is enforceable by its own terms (subsection 8) |
| Wyoming | W.S. 29-10-101(b) | One lien waiver form, “substantially the following form” | No conditional or unconditional split; the form reserves retainage and unpaid sums |
| Missouri | RSMo 429.005 | None in this section | Voids advance waivers tied to winning the contract, and says nothing prevents “contractual provisions requiring lien waivers as a condition for payment” |
What this means for a draw. In California, Texas, Arizona and Nevada, a lender or owner who accepts a home-made waiver may be holding a document the statute treats as unenforceable, which is why lenders in those states use the statutory forms. In Georgia, Florida and Wyoming the form is more flexible or more limited, and in states not in this table the waiver is whatever the draw agreement says. This is not a 50-state census: we saved the seven states above and Missouri, and we could not retrieve the legislature pages for Michigan, Mississippi, Utah or Massachusetts on November 12, 2026, so they are not scored. The Texas and Nevada texts come from public.law mirrors of the legislature's text (access dates in May 2025) because the legislature pages are script-rendered; Georgia's is a FindLaw copy. Check the current section before relying on a clause, and talk to a lawyer licensed in your state: this is analysis of public documents, not legal advice.
A $400,000 build in five draws (our arithmetic)
We use Ledger because it is the lender in our sample that prints both a draw fee and a sample rate. Assumptions: a $400,000 construction budget (land bought separately), released in five draws on a 10-month build, interest only on the drawn balance at 11%, which is the rate in Ledger's own sample schedule, not a quote. Each draw is funded at the start of its month and sits for two months.
Five draws on a $400,000 budget, interest at 11% on the drawn balance (our arithmetic)
| Draw | Share of budget | Amount | Cumulative drawn | Interest for its two months |
|---|---|---|---|---|
| 1. Foundation | 15% | $60,000 | $60,000 | $1,100 |
| 2. Framing | 30% | $120,000 | $180,000 | $3,300 |
| 3. Dry-in and rough-in | 20% | $80,000 | $260,000 | $4,767 |
| 4. Interior finishes | 20% | $80,000 | $340,000 | $6,233 |
| 5. Final and certificate of occupancy | 15% | $60,000 | $400,000 | $7,333 |
| Total | 100% | $400,000 | $22,733 |
Add Ledger's published draw fee of $350 per draw ($1,750 for five) and a typical $150 to $350 status inspection per draw ($750 to $1,750), and the draw cost is $2,500 to $3,500. Interest plus fees come to $25,233 to $26,233. If the lender had funded the whole $400,000 on day one, interest for 10 months at 11% would be $36,667, so staging the money saves $13,933 of interest (our arithmetic). A two-month overrun at the full $400,000 balance adds $7,333 of interest, so the lender's extension terms matter more than the exact draw fee. Ledger's page also says its holdback is usually 5-10% of each draw; on the $80,000 draws above that is $4,000 to $8,000 each, released at the end, which you must be able to finance until then.
What a reader can do with this
- Ask for the draw fee schedule in writing before you pick a lender. Seven of the eight lenders we read print no dollar draw fee. Ask for the draw fee, the inspection fee, the wire fee, the number of draws included and the holdback percentage.
- Plan fewer, larger draws. Each Ledger draw costs $350 plus inspection; ten draws instead of five would add $2,500 to $3,500 on our example (our arithmetic).
- Check your state's form before the first draw. If you build in California, Texas, Arizona or Nevada, ask your contractor and every subcontractor to use the statutory conditional form for each draw and the unconditional form for the prior draw once the payment has cleared.
- Sign only the conditional form until the money is in your contractor's account. An unconditional waiver in Texas may not be required unless the payment was received (Property Code 53.283).
- Keep a reserve for the holdback. If a lender keeps 5 to 10 percent of every draw until the end, your contractor carries that cash for months.
If you are comparing lenders for a ground-up build or a heavy rehab, the box below lists three that publish their terms. Compare their draw rules against the table above, and see our fix-and-flip lender comparison and the ADU construction loan page for the other loan types.
FAQ
Sources, all read November 12, 2026: lender pages of Ledger, Pimlico Capital, Cetan Funds, Lima One Capital, Sound Capital, Backflip, AHL and RCN Capital; Redwood Trust Form 10-K for 2025 (accession 0000930236-26-000007); Velocity Financial Form 10-K for 2025 (accession 0001193125-26-102677) and Form 10-Q for September 30, 2026 (accession 0001193125-26-450404); HUD Mortgagee Letter 2026-06 (June 23, 2026) and HUD Handbook 4000.1; California Civil Code 8132, 8134, 8136 and 8138; Texas Property Code 53.281 to 53.284 (public.law copy); Arizona A.R.S. 33-1008; Nevada NRS 108.2457 (public.law copy); Georgia O.C.G.A. 44-14-366 (FindLaw copy); Florida Statutes 713.20; Wyoming W.S. 29-10-101; Missouri RSMo 429.005. This is analysis of public documents, not investment, legal or tax advice.
Keep reading.
- 0120 min read
2026 Conforming Loan Limits by County: $832,750 Baseline, $1,601,750 for Four Units, 2027 Not Yet Out
FHFA's 2026 county file: 3,075 of 3,196 standard-area counties sit at $832,750 for one unit. Limits for 2 to 4 units, the 38 ceiling counties, 2027 status.
- 0222 min read
Hines Global Income Trust (HGIT) Q3 2026 10-Q: NAV $9.77, 6.9M Shares Redeemed, 18% of Payouts From Operations
HGIT 10-Q, Nov 13, 2026: NAV $9.77 at Oct 31, 6,858,361 shares redeemed in Q3 (all requests), operations funded 18% of payouts, debt $2.54B.
- 0323 min read
Mezzanine Loans 2026: 1.5% of Credit REIT Loans in Q3 10-Qs
Mezzanine and subordinate loans were $943.8M of $62.0B of loans at 11 mortgage and credit REITs on Sept 30, 2026: 1.81% listed, 0.62% non-traded.